Installation guide
19
(7) Connecting the power communication cables
Process photo Work details
Things to obey
(installer)
Connect the
power
communication
cable to the
indoor unit.
Use a ring terminal to
make a connection.
Check if the ring terminal
is used.
(8) Insulation works
Process photo Work details
Things to obey
(installer)
Pipe insulation
works.
Do not damage the
insulation materials.
Check the heat
preservation and the
slope.
(9) Insulation works
Process photo Work details
Things to obey
(installer)
Indoor unit
wrapping.
Wrap the indoor unit with
polythene to avoid any
dust, due to other work
progress in the vicinity.
Check the indoor unit
wrapping status.
7) Outdoor unit installation
(1) Vibration-proof board installation
Process photo Work details
Things to obey
(installer)
Mount the
outdoor
machine in the
correct
location by
referring to the
diagram.
- Acquire levelness of the
vibration proof board.
- Accurate measurement
and safe mounting.
Check if it is in accordance
with the diagram. Check
the levelness.